Cryogenic Energy Storage Facility BESS

Carrington, Greater Manchester

The client encountered low grade PFA subgrades on site, and high piling rig loads were anticipated. Tensar's mechanically stabilised working platform incorporating Tensar InterAx geogrid helped to save construction time, costs and carbon in stabilising the platform. 

Benefits

  • 14% construction cost savings compared to non-stabilised solution
  • 49% savings in construction time
  • 52% reduction of CO2 construction emissions compared to non-Tensar solution
Client's Challenge
  • Low strength PFA subgrades encountered on site.
  • High piling rig loads anticipated.